ABOUT THIS PROJECT

Kilgore was selected by a major oil company to perform the demolition of several structures within their processing refinery.

The scope of this project was to perform demolition activities, and the goal of the work was to remove inactive portions of the plant, segregate materials, minimize waste, and recycle or reclaim certain other items for beneficial reuse.

Work under this contract was to demolish and remove all unsold, out-of-service equipment and associated infrastructure, including:

  • Oil exchangers
  • Fin-fans
  • Crude oil transfer pumps
  • Supply tanks and vessels
  • Degrassers
  • Scrubbers
  • Pipe racks
  • Pumps
  • Sumps
  • Miscellaneous filters