Kilgore International constructed a 500kV switchyard for the TECO Power Services Gila River Power Plant. The switchyard was constructed on a prepared pad that spanned over one-half mile in length and was hailed as one of the largest in the world. Kilgore International installed over 800 drilled piers and 5,600 cubic yards of concrete.

All back feed dates were met on-time and as scheduled.